This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, August 15, 2012

Question no 1642: Calibration

In SAP PM as of ECC6.0, for Calibration Maintenance Planning, in order to automatically record measuring documents into measuring points from results recording of inspection lot, what setup is necessary ?

(only one answer)

A)    set the automatic on recording parameter indicator in the measuring point category.
B)    set the automatic on recording parameter indicator in the maintenance plan category.
C)    link the inspection characteristics to the measuring point.
D)    assign the the class characteristics used to create the measuring point to the inspection characteristics used in the calibration plan.
E)    assign an appropriate confirmation profile to the user.
.

2 comments:

  1. One of the main integration of PM-QM is Linking the Inspection Characteristics to the Class Characteristics of the Measuring Point. In this way, when the Results Recording is entered for the Inspection Characteristics in the Inspection Plan; the system will automatically write a measuring document via the class characteristics for the equipment concerned.

    ReplyDelete

Note: Only a member of this blog may post a comment.