This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, August 5, 2012

Question no 1634: Costing Relevancy

In SAP PM ECC6.0, which of the following statement is true about Costing Relevancy setting in the Plant Maintenance ?

(more then one answers)

A)   You can change it in the component detail in the Maintenance order for Stock items.
B)   You can change it in the component detail in the Bills of Material.
C)   You can change it in the component detail in the Maintenance order for Non-Stock items.
D)   You can change it in the operations detail in the Maintenance order for control key PM01.
E)   You can change it in the operations detail in the Maintenance order for control key PM02.
.


3 comments:

  1. A, B, C) Costing Relevancy in the Component detail in the Maintenance order can be changed for the standard Plant Maitnenance Order Types. Similarly, the Costing Relevancy in the BOM item detail can be changed.

    ReplyDelete
  2. D, E) However, the Costing Relevancy for the Control Key is locked when assigned to the Maintenance Operations. In fact, none of the data fields in the Control Key can be changed in the application level.

    ReplyDelete

Note: Only a member of this blog may post a comment.