In SAP PM ECC6.0 EhP1, which of the following are SAP delivery Planning indicators for the Plant Maintenance Order Type ?
(more then one answers)
A) Planned Orders.
B) Unplanned Orders.
C) Immediate Orders.
D) Corrective Orders.
E) Preventive Orders.
.
(more then one answers)
A) Planned Orders.
B) Unplanned Orders.
C) Immediate Orders.
D) Corrective Orders.
E) Preventive Orders.
.
Planning indicators are fixed delivered by SAP. However, you can default the Planning Indicators in the following customizing:
ReplyDeleteIMG - PM/CS - Maint/Serv Processing - Maint/Serv Orders - Functions and Settings for Order Types - Define Default Values for Planning Indicator for Each Order Type.
You can use PMIS t-code "MCI3" Location Standard Analysis to analyze number of order for each indicators.