In SAP MM and PP ECC6.0, determine the final lot size by evaluating the following planning data ?
Gross Requirement is 1002
Minimum quantity is 0
Maximum quantity is 1000
Rounding is 10
No other procurement element exist at the time of planning.
(only one answer)
A) A planned order of 1000.
B) A planned order of 1012.
C) A planned order of 1000 and another planned order of 10.
D) A planned order of 1008.
E) A planned order of 1010.
.
Gross Requirement is 1002
Minimum quantity is 0
Maximum quantity is 1000
Rounding is 10
No other procurement element exist at the time of planning.
(only one answer)
A) A planned order of 1000.
B) A planned order of 1012.
C) A planned order of 1000 and another planned order of 10.
D) A planned order of 1008.
E) A planned order of 1010.
.
The Maximum quantity lot sizing rule is fulfilled first and therefore a planned order of 1000 is first created. The balance requirement of 2 is fulfilled by rounding of 10 since there is no minimum quantity.