In SAP MM and PP ECC6.0, determine the final lot size by evaluating the following planning data ?
Gross Requirement is 1002
Minimum quantity is 20
Maximum quantity is 1000
Rounding is 12
No other procurement element exist at the time of planning.
(only one answer)
A) A planned order of 1000.
B) A planned order of 1012.
C) A planned order of 1000 and another planned order of 12.
D) A planned order of 1008.
E) A planned order of 1000 and another planned order of 20.
.
Gross Requirement is 1002
Minimum quantity is 20
Maximum quantity is 1000
Rounding is 12
No other procurement element exist at the time of planning.
(only one answer)
A) A planned order of 1000.
B) A planned order of 1012.
C) A planned order of 1000 and another planned order of 12.
D) A planned order of 1008.
E) A planned order of 1000 and another planned order of 20.
.
First it has to create an order of 1000 due to the maximum quantity per order. The remaining 2 cannot be fulfilled by rounding to 12 because there is a minimum quantity of 20 to adhere to; therefore, we expect an order of 20 to be created.