Question no 1917 : Storage Location MRP

In SAP MM and PP ECC6.0, Storage Location MRP allows you to setup which of the following ?

(more then one answers)

A)    A storage location to be planned separately.
B)    A different special procurement for the storage location.
C)    A different MRP type for the storage location.
D)    Ignore QI stock and Block stock from a storage location.
E)    Ignore a storage location stock from MRP. 

2 comments:

  1. There are 4 fields in the MRP4 storage location view:
    . Plan separately or Ignore planning indicator.
    . Special procurement.
    . Re-Order point.
    . Replenishment quantity.