In SAP MM and PP ECC6.0, which of the following parameters at not at the MRP Area view but at the Plant level?
(more then one answers)
A) Procurement type.
B) Special procurement key.
C) Lot size.
D) MRP strategy.
E) MRP controller.
.
(more then one answers)
A) Procurement type.
B) Special procurement key.
C) Lot size.
D) MRP strategy.
E) MRP controller.
.
Procurement type is controlled by the Material Type and therefore set at the Plant level MRP view.
ReplyDelete