In SAP PM ECC6.0, use the following capacity header data to calculate the total available capacity ?
Start 07:00
End 17:00
Capacity Utilization 60
Length of breaks 01:00
No. of individual capacity 4
(only one answer)
A) 05.40 hours
B) 36.00 hours
C) 09.00 hours
D) 21.60 hours
E) 24.00 hours
.
Start 07:00
End 17:00
Capacity Utilization 60
Length of breaks 01:00
No. of individual capacity 4
(only one answer)
A) 05.40 hours
B) 36.00 hours
C) 09.00 hours
D) 21.60 hours
E) 24.00 hours
.
Answer: D
ReplyDelete((17 - 7) - 1) x (60/100) x 4 = 21.60 hours
ReplyDelete