In SAP PP-PI as at ECC6.0 EhP6, which of the following setting 'locks-in' whether X-Steps and/or Process Instructions are allowed for the Master Recipe ?
(only one answer)
A) Routing usage.
B) Default value profile.
C) Plant parameter.
D) Production version.
E) Production scheduler profile.
.
(only one answer)
A) Routing usage.
B) Default value profile.
C) Plant parameter.
D) Production version.
E) Production scheduler profile.
.
Answer: B
ReplyDeleteIMG - Production Planning for Process Industries - Master Data - Master Recipe - Settings for the Task List Type - Define Profiles with Default Values.
ReplyDelete(in the Process Management section, select Process Instruction Maintenance option
O for XSTEPS optional
X for XSTEPS
'' for Process Instructions
Assign value of the Profile as Parameter ID 'PIN' to the user in SU3 or SU01 parameter tab