This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, March 31, 2021

Question no 3822 : "ND" MRP Type

In SAP MM/PP as at ECC6.0 EhP6, setting MRP1 data view in the Material Master to "ND" (No Planning), which of the other fields is mandatory in the MRP data views ?

(only one answer)

A)  Lot Size Key.
B)  Scheduling Margin Key.
C)  Planned Delivery Time.
D)  AV Check Group.
E)  MRP Strategy.
.

Answer: C

In ECC with MRP Type "NB", only the Planned Delivery Time is Mandatory.
In ECC with a valid MRP Type such as "PD" or "VB" etc:
Lot size is mandatory (MRP1)
Procurement type is mandatory (MRP2)
Planned Delivery time is mandatory (MRP2)
Scheduling Margin key is mandatory (MRP2)

In S/4, the mandatory fields for MRP views are different. 