In SAP MM/PP for MRP as at ECC6.0 EhP6, which of the following is mandatory in MRP 1 and MRP 2 data view when activating a Material for Material Planning?
(only one answer)
A) MRP Type.
B) Lot Size Key.
C) Procurement Type.
D) Special Procurement Key.
E) Planned Delivery Time.
.
Answer: D
With a valid MRP Type for MRP run, on the list above, the Special Procurement Key is optional.