Question no 3811 : MRP Area Type

In SAP PP as at ECC6.0 EhP6, which of the following are valid MRP Area Types ?


(more than one answers)

A)  Plant.
B)  Storage Location.
C)  Vendor.
D)  Purchasing Organization.
E)  Scope of Planning.
.

Answers: A, B, C

A) MRP area for MRP Type = Plant is reserved for the Plant code of 4 alphnumeric.
B) MRP area for Storage Location is 5 or more alphanumeric and one or more Storage Location can be assigned to it.
C) MRP area for Vendor is only for one Vendor.

User defined MRP areas for storage locations and for subcontractors and you have assigned the materials, the plant MRP area is reduced by exactly this number of subcontractors and storage locations. This is because they are now to be planned separately.

IMG - Production - MRP - Master Data - Areas - Define MRP Areas for Plant/Storage Locations
IMG - Production - MRP - Master Data - Areas - Define MRP Areas for Subcontractors
...
When creating MRP Area for Storage Location and Subcontractors, it must be more than 4 alphanumeric as the 4 alpha code is reserved for Plant definition = MRP Area (eg: Plant = 1010 = MRP Area = 1010).
In S/4, Storage Location MRP setup in the Material Master MRP4 data view is no longer possible and MRP Area is the next logical choice of Planning at the Storage Location level.