Question no 3814 : MRP Run

In SAP MM/PP as at ECC6.0 EhP6, which of the following are considered in Scope of Planning at MRP run ?


(more than one answers)

A)  Sequence of MRP run for a list of Plants.
B)  Sequence of MRP run for a list of MRP Areas.
C)  Sequence of MRP run for a list of Material Groups.
D)  Sequence of MRP run for a list of Material Types.
E)  Sequence of MRP run for a list of Supply Areas.
.

Answers: A, B

The Plants or MRP areas that are combine in a scope of planning are planned together in a total planning run. This has the advantage that you no longer need to create a background job for each work individually.
It is available in MD01 and MDBT.
IMG - Production - MRP - Planning - Define Scope of Planning for Total Planning