In SAP MM/PP as at ECC6.0 EhP6, what does MRP control features MD01 contains which MD02 does not have ?
(more than one answers)
A) Regenerative MRP run.
B) Net Change MRP run.
C) Not change within horizon MRP run.
D) Scope of Planning.
E) User Exit Key.
.
Answers: A, D, E
MD01 contains the following where MD02 does not have
. Regenerative MRP run.
. Scope of Planning.
. User Exit Key.
. Parallel Processing.
A) Regenerative MRP run.
B) Net Change MRP run.
C) Not change within horizon MRP run.
D) Scope of Planning.
E) User Exit Key.
.
Answers: A, D, E
MD01 contains the following where MD02 does not have
. Regenerative MRP run.
. Scope of Planning.
. User Exit Key.
. Parallel Processing.