Question no 3809 : Scheduing Margin Key

In SAP MM/PP as at ECC6.0 EhP6, which of the following time element is not part of the parameter within the Scheduling Margin Key ?


(only one answer)

A)  Opening period.
B)  Float Before Production.
C)  Float After Production.
D)  Release Period.
E)  Safety Time.
.

Answer: E

Safety Time in the MRP 2 data view.
IMG - Production - MRP - Plant Parameter - Carry out Overall Maintenance of Plant Parameters
check the Floats
Key that the system uses to determine the floats required for scheduling an order. You define the following floats with the scheduling margin key:
opening period
float after production (only in the case of in-house production)
float before production (only in the case of in-house production)
release period (only in the case of production order management)
Floats are maintained in workdays.