Question no 3242 : Preventive Maintenance Plan Maintenance Item structure

In SAP PM as at ECC6.0 EhP6, the following regarding the Maintenance Item in a Preventive Maintenance Plan are Correct EXCEPT one ?

(only than one answer)

A)  A settlement rule can be entered in the Maintenance Item.
B)  A maintenance item can be assigned with one or more Technical Objects.
C)  A maintenance task list is optional in a Maintenance item even if the call object is a Maintenance Order.
D)  A maintenance must have at least one Maintenance item.
E)  Each maintenance item can have its own scheduling parameter.
.