In SAP PP MRP Area as at ECC6.0 EhP6, which of the following data fields are mandatory at the MRP Area level parameter in the Material Master ?
(more than one answers)
A) MRP Group.
B) MRP Controller.
C) MRP Type.
D) Special Procurement Key.
E) Planned Delivery Time.
.
(more than one answers)
A) MRP Group.
B) MRP Controller.
C) MRP Type.
D) Special Procurement Key.
E) Planned Delivery Time.
.
Answer: B, C
ReplyDeleteB, C) MRP Type, MRP Controller, and Lot Size key.