In SAP PM as at ECC6.0 EhP6, which of the following statements are TRUE about Historical Orders in Plant Maintenance ?

(more than one answers)

A)  It can be settled to a Statistical Cost Object for information purpose.
B)  Material and actual withdrawal quantity can be entered.
C)  Non-Stock History Purchase Order can be entered.
D)  Actual work can be entered as Operations.
E)  Actual costs can be entered as Cost Elements.
.

1 comment:

  1. A, E) Cost can be entered only as value categories and not cost element and no settlement rule is allowed.

    B, D) Actual material and withdrawal quantities with Actual work hours can be entered but are all statistical.

    C) Purchase Orders cannot be entered in the Historical Orders.