In SAP PP MRP as at ECC6.0 EhP6, which of the following will happen when a Material Master has been created with a MRP data view with a valid MRP type ?

(more than one answers)

A)  The Planning File entry will be automatically created.
B)  The NETCH and NETPL indicator will be set in the Planning File entry.
C)  Only the NETCH indicator will be set in the Planning File entry.
D)  The Low level code will be set to 000 for the Mateial in the Planning File entry.
E)  The Low level code will not be updated until the material is assigned to a BOM.
.

2 comments:

  1. A) Planning file entry is created for a material whenever there is a valid MRP type.

    B, C) both NETCH and NETPL indicators are set when the planning file entry is first created.

    D, E) LLC is set at 999 when the planning file entry is first created.

    ReplyDelete