Question no 2271 : Inspection Stage Change

In SAP QM, which of the following is used to change the inspection stages as a result of the quality level ?

(only one answer)

A)     Sampling Scheme.
B)     Inspection Point.
C)     Dynamic Modification Factor.
D)     Status Profile.
E)     Inspection Method.
.

2 comments:

  1. The DMR assigned to the Material Master Inspection Type at the QM view or the Inspection Plan Header is used to manage the changing inspection stages as a result of the quality level.