In SAP QM, which of the following is used to change the inspection stages as a result of the quality level ?
(only one answer)
A) Sampling Scheme.
B) Inspection Point.
C) Dynamic Modification Factor.
D) Status Profile.
E) Inspection Method.
.
(only one answer)
A) Sampling Scheme.
B) Inspection Point.
C) Dynamic Modification Factor.
D) Status Profile.
E) Inspection Method.
.
Answer: C
ReplyDeleteThe DMR assigned to the Material Master Inspection Type at the QM view or the Inspection Plan Header is used to manage the changing inspection stages as a result of the quality level.