In SAP PM ECC6.0, which of the following type of Maintenance Plan can have only one Maintenance Item ?
(more then one answers)
A) IP41 Single Cycle Plan.
B) IP42 Strategy Plan.
C) IP43 Multiple Counter Plan.
D) IP40 Service Procurement.
E) IP50 Service Contract.
.
(more then one answers)
A) IP41 Single Cycle Plan.
B) IP42 Strategy Plan.
C) IP43 Multiple Counter Plan.
D) IP40 Service Procurement.
E) IP50 Service Contract.
.
So far at ECC6.0, only the Single Cycle Plan and Strategy Plan allows multiple maintenance items.
ReplyDelete