In SAP PM/CS ECC6.0, If a Maintenance Item is registered with multiple technical objects (example: 3 equipment), what is expected of the scheduling results when maintenance is due for the Maintenance Item ? (assuming that the task list contains 3 operations and the call object is a maintenance order)
(only one answer)
A) 3 maintenance order is generated, one for each equipment.
B) 1 maintenance order is generated with 9 operations for the 3 equipments.
C) 1 maintenance order is generated with 3 operations with the original time from the task list for the 3 equipments.
D) 1 maintenance order is generated with 3 operations with the (original time x 3) from the task list for the 3 equipments.
E) 3 maintenance order is generated, one for each equipment provided a configuration is set for the maintenance category used to create the maintenance plan.
(only one answer)
A) 3 maintenance order is generated, one for each equipment.
B) 1 maintenance order is generated with 9 operations for the 3 equipments.
C) 1 maintenance order is generated with 3 operations with the original time from the task list for the 3 equipments.
D) 1 maintenance order is generated with 3 operations with the (original time x 3) from the task list for the 3 equipments.
E) 3 maintenance order is generated, one for each equipment provided a configuration is set for the maintenance category used to create the maintenance plan.
Answer: C