In SAP PP Kanban ECC6.0, which of the following are supported in the External Replenishment of the Kanban Process ?

(more then one answers)

A)   Purchase Orders
B)   Delivery schedules
C)   Stock transport orders
D)   Stock transport scheduling agreements
E)   Source lists

2 comments:

  1. In external procurement, you can work with replenishment using:
    . purchase orders
    . delivery schedules
    . stock transport orders
    . stock transport scheduling agreements
    . source lists
    . container control/MRP
    . summarized JIT calls