In SAP PP Kanban ECC6.0, which of the following are supported in the External Replenishment of the Kanban Process ?
(more then one answers)
A) Purchase Orders
B) Delivery schedules
C) Stock transport orders
D) Stock transport scheduling agreements
E) Source lists
.
(more then one answers)
A) Purchase Orders
B) Delivery schedules
C) Stock transport orders
D) Stock transport scheduling agreements
E) Source lists
.
Answer: A, B, C, D, E
ReplyDeleteIn external procurement, you can work with replenishment using:
ReplyDelete. purchase orders
. delivery schedules
. stock transport orders
. stock transport scheduling agreements
. source lists
. container control/MRP
. summarized JIT calls