Question no 2255 : Results Recording for Maintenance Calibration

In SAP PM/CS ECC6.0, at the Calibration results entry using Result Recording QE51N, what are possible ?

(more then one answers)

A)    Change the Modification Factor of the Maintenance Plan.
B)    Set the Equipment Status.
C)    Enter confirmation hours for the operation.
D)    Change the Valuation suggest by the system.
E)    Close the Maintenance Order.
.

1 comment:

  1. In QE51N, after entering the calibration results, you can change the suggested valuation results. SAP also allows the technician to confirm the hours used for the calibration process.