Question no 2257 : Framework Order

In SAP MM ECC6.0, which of the following Procurement scenario uses the "Framework Order" order type ?

(more then one answers)

A).   Blanket PO.
B).   Subcontrating PO.
C).   Invoicing Plan.
D).   Consignment PO.
E).   Pipeline PO.
.

2 comments:

  1. Both Blanket PO and Invoicing Plan requires the validity period at the PO header from the "FO" PO order type.