In SAP MM and PP ECC6.0, "NETCH" is which of the following ?
(only one answer)
A) Net change within the planning horizon.
B) Net change within the time fence.
C) Net change in the total horizon.
D) Net change outside the time fence.
E) Net change outside the planning horizon.
.
(only one answer)
A) Net change within the planning horizon.
B) Net change within the time fence.
C) Net change in the total horizon.
D) Net change outside the time fence.
E) Net change outside the planning horizon.
.
Answer: C
ReplyDeleteNETCH of "Net Change" Planning indicator tracks changes regardless of time line (ie: total horizon), this includes planning parameter changes in the material master and customizing.