In SAP MM and PP ECC6.0, which of the following MRP elements are considered for available supply to the MRP run ?
(more then one answers)
A) RFQ.
B) Firmed Purchase Requisitions with vendor assigned.
C) MRP generated Purchase Requisitions.
D) Delivery Schedule for Scheduling Agreement.
E) Purchase Requisitions without vendor assigned.
.
(more then one answers)
A) RFQ.
B) Firmed Purchase Requisitions with vendor assigned.
C) MRP generated Purchase Requisitions.
D) Delivery Schedule for Scheduling Agreement.
E) Purchase Requisitions without vendor assigned.
.
Purchase Requisitions that are manually generated or MRP generated and with or without vendor assigned are considered as supply by the MRP system.