In SAP MM and PP ECC6.0, which of the following MRP elements are considered for available supply to the MRP run ?

(more then one answers)

A)     RFQ.
B)     Firmed Purchase Requisitions with vendor assigned.
C)     MRP generated Purchase Requisitions.
D)     Delivery Schedule for Scheduling Agreement.
E)     Purchase Requisitions without vendor assigned. 
.

1 comment:

  1. Purchase Requisitions that are manually generated or MRP generated and with or without vendor assigned are considered as supply by the MRP system.