In SAP MM and PP ECC6.0, which of the following characteristics are TRUE about MRP Area ?
(more then one answers)
A) An MRP Area can be assigned to one or more storage locations.
B) Each MRP Area can only be assigned with one default goods receipt storage location.
C) An MRP Area can be assigned to one or more vendors.
D) An MRP Area must be created no less then 4 alphanumeric characters.
E) An MRP Area must always be created for a Plant.
.
(more then one answers)
A) An MRP Area can be assigned to one or more storage locations.
B) Each MRP Area can only be assigned with one default goods receipt storage location.
C) An MRP Area can be assigned to one or more vendors.
D) An MRP Area must be created no less then 4 alphanumeric characters.
E) An MRP Area must always be created for a Plant.
.
Answer: A, B, D, E
ReplyDeleteAn MRP Area can represent more then one storage location, but each MRP Area can only represent one vendor.