In SAP MM and PP ECC6.0, the result of an MRP run can generate which of the following ?
(more then one answers)
A) Purchase Requisition without a vendor.
B) Purchase Requisition with a vendor.
C) Contract Release Order.
D) Delivery Schedule for a Scheduling Agreement.
E) Purchase Requisition assigned to a Contract.
.
(more then one answers)
A) Purchase Requisition without a vendor.
B) Purchase Requisition with a vendor.
C) Contract Release Order.
D) Delivery Schedule for a Scheduling Agreement.
E) Purchase Requisition assigned to a Contract.
.
Answer: A, B, D, E
ReplyDeleteBasically MRP can only generate Planned Order and Purchase Requisitions.
ReplyDeleteHowever, when the Source List is setup with the right MRP indicator; source determination can take place during MRP run and therefore the following are possible:
. PR assigned to Contract
. PR assigned to Scheduling Agreement
. Delivery Schedule for Scheduling Agreement