Question no 1941 : Safety Stock

In SAP MM and PP ECC6.0, the Safety Stocks presents the following features ?

(more then one answers)

A)    Stocks cannot go below the Safety Stocks level, replenishment will be generated if that happens.
B)    When Stocks go below the Safety Stocks, the planning file indicators will be flagged.
C)    Safety Stocks can be automatically calculated via the MRP type configuration.
D)    If the Re-Order Point is implemented, the Re-Order Point Qty must be below the safety stock.
E)    The Safety Stock is illustrated as a percentage of Re-Order Point Quantity.
.

1 comment:

  1. In Re-Order Point Planning, the ROP Quantity must be above the safety stock level. The Safety Stock is always presented as a Quantity in the MRP2 view.

    ReplyDelete