Question no 1871 : GR Processing Time

In SAP MM and PP ECC6.0, goods receipt processing time is used to determine ____________ .

(only one answer)

(A)   Delivery date
(B)   Opening date
(C)   Closing date
(D)   End date
(E)   Stock available date

2 comments:

  1. GR Processing Time is an internal lead time for QC and Store-in to determine the Stock Available Data. It is setup in the MRP2 view.