In SAP MM and PP ECC6.0, goods receipt processing time is used to determine ____________ .
(only one answer)
(A) Delivery date
(B) Opening date
(C) Closing date
(D) End date
(E) Stock available date
.
(only one answer)
(A) Delivery date
(B) Opening date
(C) Closing date
(D) End date
(E) Stock available date
.
Answer: E
ReplyDeleteGR Processing Time is an internal lead time for QC and Store-in to determine the Stock Available Data. It is setup in the MRP2 view.