In SAP MM ECC6.0, a global enterprise has plants located world wide producing similar products while contracts for all plants are being negotiated at the head quarters using a quantity contract; some of the raw materials may have different prices due to plant logistics. What would be the possible characteristics of the central contract for its raw materials ?
(only one answer)
(A) Quantity Central contract without plant, with plant conditions.
(B) Quantity Central contract without plant with info record at the plant level.
(C) Individual contracts for each material at each plant but created at the central purchasing organization.
(D) One central quantity contract with contract line items for each plant.
(E) Value Central contract without plant with plant conditions.
.
(only one answer)
(A) Quantity Central contract without plant, with plant conditions.
(B) Quantity Central contract without plant with info record at the plant level.
(C) Individual contracts for each material at each plant but created at the central purchasing organization.
(D) One central quantity contract with contract line items for each plant.
(E) Value Central contract without plant with plant conditions.
.
Answer: A
ReplyDeleteCentral Contract without Plant can be created by the Central Purchasing Organization (Reference Purchasing Organization) with or without Plant Conditions. The Contract Release Order (or PO) can then be released by associated Purchasing Organization.
ReplyDelete