In SAP MM and PP ECC6.0, general sequence of Consumption Based MRP run is depicted by which of the following sequence ?
(only one answer)
(A) Net Calculation -> Lot sizing -> Procurement type -> Procurement dates
(B) Net Calculation -> Procurement type -> Lot sizing -> Procurement dates
(C) Net Calculation -> MRP Explosion -> Lot sizing -> Procurement type -> Procurement dates
(D) Net Calculation -> Lot sizing -> Procurement type -> Procurement dates -> BOM Explosion
(E) Net Calculation -> Lot sizing -> Procurement dates -> Procurement type -> BOM Explosion
.
(only one answer)
(A) Net Calculation -> Lot sizing -> Procurement type -> Procurement dates
(B) Net Calculation -> Procurement type -> Lot sizing -> Procurement dates
(C) Net Calculation -> MRP Explosion -> Lot sizing -> Procurement type -> Procurement dates
(D) Net Calculation -> Lot sizing -> Procurement type -> Procurement dates -> BOM Explosion
(E) Net Calculation -> Lot sizing -> Procurement dates -> Procurement type -> BOM Explosion
.
Answer: A
ReplyDeleteCBP 4 steps:
ReplyDelete1) Net Requirement Calculation (MRP type segment MRP1 view and Safety Stock in MRP2 view)
2) Lot Sizing (MRP 1 view)
3) Procurement decision (MRP 2 view, Procurement type and special procurement keys)
4) Procurement dates (MRP 2 view, lead times)