Question no 1870 : MRP Parameter

In SAP MM and PP ECC6.0, most of the planning parameters for MRP run at setup at the plant parameter, groups of material within the same plant have similar planning parameter characteristics. Which of the following you would recommend looking at to setup planning parameters below the plant level.

(only one answer)

(A)   MRP controller.
(B)   MRP group.
(C)   MRP storage location.
(D)   MRP area.
(E)   MRP procurement key.
.

2 comments:

  1. The MRP group is an organizational object which is used to assign special control parameters for planning to a group of materials.