In SAP MM ECC6.0, which of the following statements are not true about outline agreements ?
(more then one answers)
(A) Purchase orders are used to release contract items.
(B) Purchase orders are used to release contract and scheduling agreement items.
(C) Goods receipt against contracts are not possible.
(D) Goods receipt against contracts are possible provided the delivery schedules are created within the contract and not using purchase orders.
(E) Goods receipt is done against the purchase orders but invoice verification is with reference to the contract as the prices are stored in the contract.
.
(more then one answers)
(A) Purchase orders are used to release contract items.
(B) Purchase orders are used to release contract and scheduling agreement items.
(C) Goods receipt against contracts are not possible.
(D) Goods receipt against contracts are possible provided the delivery schedules are created within the contract and not using purchase orders.
(E) Goods receipt is done against the purchase orders but invoice verification is with reference to the contract as the prices are stored in the contract.
.
The Contract Release Order to the Contract are Purchase Orders. Scheduling Agreement uses delivery schedule for quantity releases.
ReplyDeleteIn SAP, you can perform goods receipt with reference to Purchase Orders or Scheduling Agreement Delivery Schedules and not the other Purchasing Documents.