In SAP S/4, what could have caused the ERROR below when trying to apply the Change Master to change the Routing ?
(only one answer)
A) The Change Master was not set with an appropriate Release Key
B) The Change Master was set with an Inactive Change master Status.
C) The Change Master was not activated for changes to Routing.
D) The Change Master was not entered with a Reason for Change.
D) The Change Master was not entered with a Valid Date.
.
Answer: C
If the Change Master Header's "Change no. Status" is set with an "Inactive Status", then the Message "Change master status "02" does not allow changes" (Message no CC066) (note status "02" is inactive in Standard SAP IDES system)
If the Change Master was not activated to allow changes to Task List then the Message "Processing of the object not supported for Change Number "XXXX" (Message no CC061)
If the Change Master was activate for Change to Task list as well as Objects indicator BUT the Task list was not entered in the Object Management Record in the Change Master, then the Message "Generation not supported for change object" (Message no CC063)