Question no 4223 : CGFB and NOCH system status in the Production Order for OCM processing

  In SAP S/4, the following transaction is COCM1, in which Stage of the OCM process that the system writes the System status "CGFB" and "NOCH" to the Production Order ?


(only one answer)

A) Assigned the MTO Sales Order to the MTO Production Order
B) Simulation Order
C) Determine Changes
D) Check Changes
E) Change Original Order
.

Answer: D

Step 1: Assigned the MTO Sales Order to the MTO Production Order
Step 2: Simulation Order
Step 3: Determine Changes (set "NOCH" status)
Step 4: Check Changes (set "CGFB" and "NOCH" status)
Step 5: Change Original Order (remove "CGFB" and "NOCH" status)