Question no 4206 : "Change Record" FIORI App

In SAP S/4HANA Logistics General, in the "Manage Engineering Changes" FIORI App which is to create "CHANGE RECORDS"; at what Status which the Engineering Change Master will be generated automatically by the system ? (assuming the Change Record is only entered with Description and Person Responsible)


(only one answer)

A) Start Change Process
B) Send Change Request to Approval
C) Approve Change Request
D) Start Design
E) Start Parts and BOM
.

Answer: C

There are 6 Basic Steps in the Standard "Change Record" FIORI App
Start Change Process
Send Change Request to Approval
Approve Change Request (this step auto generates the Change Master)
Start Design
Start Parts and BOM
Complete Change

It is important to note that after the Change Record is created, and in the immediate next step the Engineer entered the "Manufacturing Effective Date" (Valid from) for Record Type "Engineering Changes (S02)", the system will already be automatically generating the Change Master.

But if the "Manufacturing Effective Date" (Valid from) is left BLANK, the system will still be generating the Change Master  upon "Approval of the Change Request"; however the Valid date in the Change Master will be 31.12.9999