In SAP S/4HANA Production Planning & Execution, The following ECM for the Bill of Material can be used to do what tasks ?


(more than one answers)

A)  Change the Header Content of the BOM
B)  Apply the ECM via the BOM Group
C)  Delete an Item in the BOM
D)  Change a Quantity of a BOM item
E)   Introduce a new Document as a BOM item
.

Answer: A, B, C, D, E

Overview of ECM application to the BOM
CS02 to Change the Header Content
CS02 to Change the BOM item Content: Create, Delete, Change fields
CS01 to Create a new BOM
CS01 to Create a new BOM with next Alternative
CS05 to Make changes to BOMs in a BOM Group