This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, September 7, 2026

Question no 4205 : ECM Application to BOM Group

 In SAP S/4HANA Logistics General, The screen shot was a report for Change Master ECM1 and ECM2 via t-code CC09 (ECM Information System), select which answers correctly depicting what you see from the report ?


(more than one answers)

A)  The ECM was applied to the BOM Group which contains at least 3 Material BOM of FG100, FG200 and FG300.
B)  The BOM Group that was applied with the ECN were Variant BOMs with Technical Type "V" Variant BOM.
C)  The BOM Group that was applied with the ECN were Multiple BOMs with Technical Type "M" Multiple BOM.
D)  Material T-S101 was changed from 1 pcs to 2pcs using ECM2.
E)  A Material T-T714 was added to the FG300 using ECM2.
.

Answer: A, B, D, E

"C" is not correct because Multiple BOMs with Technical Type "M" has the same BOM Header and the Alternative BOMs are differentiated by Lot Sizes.

No comments: