Question no 3742 : Kanban triggering

In SAP PP as at ECC6.0 EhP6, which of the following can be triggered via a Kanban signal ?

(more than one answers)

A)  RFQ.
B)  Purchase Order.
C)  Production Order.
D)  Contract.
E)  Scheduling Agreement.
.
click "1 comment" to view suggested solution

1 comment:

  1. Answers: B, C

    Possible Kanban Triggers are:
    . Purchase Order (Vendor)
    . Stock Transport Order
    . Delivery Schedule for Scheduling Agreement
    . Production Order
    . Reservations for Transfers

    ReplyDelete