In SAP PP as at ECC6.0 EhP6, which of the following are correct for Work Center Capacity ?
(more than one answers)
A) A Pool Capacity can be assigned to more than one Work Centers.
B) A Work Center can have one or more Capacity Categories.
C) Only one of the Capacity Categories can be assigned in the Scheduling TAB of the Work Center.
D) Only one of the Capacity Categories can be assigned in the Costing TAB of the Work Center.
E) An Alternative Factory Calendar can be assigned to the Capacity Category different from the Plant Factory Calendar.
.
click "1 comment" for suggested solution
(more than one answers)
A) A Pool Capacity can be assigned to more than one Work Centers.
B) A Work Center can have one or more Capacity Categories.
C) Only one of the Capacity Categories can be assigned in the Scheduling TAB of the Work Center.
D) Only one of the Capacity Categories can be assigned in the Costing TAB of the Work Center.
E) An Alternative Factory Calendar can be assigned to the Capacity Category different from the Plant Factory Calendar.
.
click "1 comment" for suggested solution
Answers: A, B, C, E
ReplyDeleteA) Pool Capacity especially common labor force for several work centers can be created as Pool Capacity and to be assigned to several Work Centers.
B) A Work Center can have 1 or more Capacity Category (eg: Machine and Labor) to calculate capacity of Machine and Labor for a Production Order or Process Order.
C) In the Scheduling Tab, only one capacity category can be chosen to Scheduling Purpose.
D) The Costing TAB do not have a Capacity Category.
E) The system defaults the Plant Factory Calendar to the Work Center but it can be changed.