In MM as at ECC6.0 EhP6, which of the following are expected characteristics of Invoicing Plan ?
(more then one answers)
A) Document Type "Framework Order" with Header validity Period.
B) Goods Receipt is expected.
C) A schedule of payment is to be constructed via the Invoicing Plan Type.
D) Account Assignment "U" (Unknown) is expected of.
E) ERS indicator is expected of.
.
Click "1 comment" to view suggested solution.
(more then one answers)
A) Document Type "Framework Order" with Header validity Period.
B) Goods Receipt is expected.
C) A schedule of payment is to be constructed via the Invoicing Plan Type.
D) Account Assignment "U" (Unknown) is expected of.
E) ERS indicator is expected of.
.
Click "1 comment" to view suggested solution.
Answers: A, C, E
ReplyDeleteB) No Goods Receipt allowed (not relevant).
D) An Account Assignment (eg: Cost Center) is expected of as the Invoicing Plan PO is subjected to Auto Invoice generation from a background job when the amount is due according to the scheduled payment constructed in the PO.