In SAP PP as at ECC6.0 EhP6, which of the following is the correct Available Capacity based on the data provided ?
Work Time: 09:00 - 18:00
Break Time: 1 hour
No of Capacity: 4
Capacity Utilization: 80%
(only one answer)
A) 25.6 hours
B) 32 hours
C) 36 hours
D) 28.8 hours
E) 320 hours
.
click "1 comment" for possible solution
Work Time: 09:00 - 18:00
Break Time: 1 hour
No of Capacity: 4
Capacity Utilization: 80%
(only one answer)
A) 25.6 hours
B) 32 hours
C) 36 hours
D) 28.8 hours
E) 320 hours
.
click "1 comment" for possible solution
Answer: A
ReplyDelete(Work Time - Break Time) x no. of Capacity x Utilization / 100
(9 - 1) x 4 x 80 / 100