In SAP PP as at ECC6.0 EhP6, which of the following are the general setup required for PQC (Process Quality Control) for PP Production Order ?
(more than one answers)
A) Assignment of Inspection Point in the Routing Header.
B) Assignment of Inspection Point in the Header of the BOM.
C) Assignment of Master Inspection Characteristics in the Routing Operation.
D) Assignment of Master Inspection Characteristics in the BOM item.
E) Assignment of an appropriate Inspection Type in the Material Master QM data view.
.
Answers: A, C, E
(more than one answers)
A) Assignment of Inspection Point in the Routing Header.
B) Assignment of Inspection Point in the Header of the BOM.
C) Assignment of Master Inspection Characteristics in the Routing Operation.
D) Assignment of Master Inspection Characteristics in the BOM item.
E) Assignment of an appropriate Inspection Type in the Material Master QM data view.
.
Answers: A, C, E