This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, September 1, 2020

Question no 3729 : External Service in MM and PM

In SAP MM and PM as at ECC6.0 EhP6, the Service Master can be assigned to the following EXCEPT ?

(only one answer)

A)  Purchase Requisition item detail level.
B)  Purchase Order item detail level.
C)  Maintenance Item.
D)  General Task List Operation detail.
E)  Maintenance Notification Item level.
.

see "1 comment" for suggested solution

1 comment:

  1. Answer: E

    Except the Maintenance Notification item level where only Catalog code groups codes can be assigned (so far in ECC6 Ehp6)