In SAP PM as at ECC6.0 EhP6, which of the following standard PM Order Type is used for internal refurbishment with Valuation Type ?

(only one answer)

A)  PM01.
B)  PM02.
C)  PM03.
D)  PM04.
E)  PM05.
.

Answer: E

PM04 is standard SAP Order type of Internal Refurbishment, see IW81