Question no 3562 : Mass Replacement in Plant Maintenance

In SAP PM as at ECC6.0 EhP6, which of the following "Mass Replacement" functions are available for objects in the Task List ?

(more than one answers)

A)   Components assigned to the Task List Operation.
B)   Work Center assigned to the Task List Operation.
C)   PRT assigned to the Task List Operation.
D)   Assembly assigned to the Task List Header.
E)   Planning Plant assigned to the Task List Header.
.

Answer: B, C

CA87 Replace Work Center.
CA77 Replace PRT.