Question no 3557 : BOM Selection in MRP Run

In SAP PP MRP as at ECC6.0 EhP6, which of the following controls the selection of BOM for MRP run ?

(only one answers)

A)  Plant Parameter.
B)  MRP Group Parameter.
C)  Selection ID in the MRP 4 data view in the Material Master.
D)  It always choose the BOM with usage "1".
E)  None of the above.
.

Answer: A

Goto OPPQ, check "BOM/Routing Selection".