In SAP PM as at ECC6.0 EhP6, which of the following are created with a Planning Plant ?
(more than one answers)
A) Maintenance Work Center.
B) Maintenance Task List.
C) Maintenance Notification.
D) Maintenance Order.
E) Equipment Master.
.
Answer: B, D
A) Work Center is created with a Maintenance Plant.
C) Maintenance Notification does not work with a Plant.
D) Equipment Master need not be assigned to a Plant.
(more than one answers)
A) Maintenance Work Center.
B) Maintenance Task List.
C) Maintenance Notification.
D) Maintenance Order.
E) Equipment Master.
.
Answer: B, D
A) Work Center is created with a Maintenance Plant.
C) Maintenance Notification does not work with a Plant.
D) Equipment Master need not be assigned to a Plant.